Technology Department

TE Management Board (TEMB) Minutes 2009

Minutes Date Special topics
TEMB 1 12-Jan-09 Sector 3-4 repair status and planning ; Discussion on Technical Committee structure ; MARS 2009 calendar
TEMB 2 19-Jan-09 Sector 3-4 repair status and planning
TEMB 3 26-Jan-09 Sector 3-4 repair status and planning ; Outcome of the review of the QPS electronics upgrade ; Shutdown activities
TEMB 4 09-Feb-09 Sector 3-4 repair status and planning ; Chamonix workshop debriefing
TEMB 5 16-Feb-09 DN200 status ; SM18 splice measurements ; BTE-Desktop ; Update on 2009 budget
TEMB 6 23-Feb-09 Fellows, Associates, Students : 2009 guidelines ; Sector 3-4 repair status and planning ; Enhanced QPS status
TEMB 7 02-Mar-09 MARS tool presentation ; Sector 3-4 repair status and planning ; QPS external review highlights
TEMB 8 09-Mar-09 Sector 3-4 repair status and planning ; Highlights of the "LHC Risk Review"
TEMB 9 16-Mar-09 Sector 3-4 repair status and planning ; Highlights of the "LHC Risk Review" ; Status of workpackage outsourcing for QPS and SM18 data analysis ; Progress status on the Task Force on safety of personnel
TEMB 10 30-Mar-09 Sector 3-4 repair status and planning
TEMB 11 6-Apr-09 Sector 3-4 repair status and planning
TEMB 12 20-Apr-09 Fellows, Associates, Students: Status; Sector 3-4 repair status and planning
TEMB 13 27-Apr-09 Sector 3-4 repair status and planning
TEMB 14 11-May-09 Sector 3-4 repair status and planning
TEMB 15 18-May-09 Sector 3-4 repair status and planning
TEMB 16 25-May-09 Sector 3-4 repair status and planning; Status on contract policy
TEMB 17 08-Jun-09 Sector 3-4 repair status and planning
TEMB 18 15-Jun-09 Sector 3-4 repair status and planning; Budget status; Preparation of the manpower planning day
TEMB 19 22-Jun-09 LHC consolidation: status and planning; LHC hardware commissioning status
TEMB 20 29-Jun-09 Status of FSU contract renewal; LHC consolidation: status and planning; LHC hardware commissioning status
TEMB 21 6-Jul-09 HIE-ISOLDE Organization; Progress Report on QPS; LHC consolidation: status and planning; LHC hardware commissioning status; Training statistics
TEMB 22 20-Jul-09 LHC consolidation: status and planning; LHC hardware commissioning status
TEMB 23 27-Jul-09 Electrical cut in sector 7-8 on 17 July a.m.; LHC hardware commissioning status
TEMB 24 3-Aug-09 MP3 activity report
TEMB 25 17-Aug-09 MP3 activity report and hardware commissioning
TEMB 26 24-Aug-09 MP3 activity report and hardware commissioning;
TEMB 27 31-Aug-09 Consolidation of the superconducting magnet test facility
TEMB 28 14-Sep-09 MP3 activity report and hardware commissioning; Information from Enlarged Directorate; Presentation "Nouvelle Politique des contrats"
TEMB 29 21-Sep-09 MP3 activity report and hardware commissioning
TEMB 30 28-SEP-09 MP3 activity report and hardware commissioning
TEMB 31 5-Oct-09 MP3 activity report and hardware commissioning; "La consignation cryogénique"
TEMB 32 12-Oct-09 MP3 activity report and hardware commissioning
TEMB 33  19-Oct-09 MP3 activity report and hardware commissioning
TEMB 34 2-Nov-09 MP3 activity report and hardware commissioning; 2009 Mini-TEEP; LHC operational consolidation
TEMB35 9-Nov-09 HR recruitment initiative; MP3 activity report and hardware commissioning
TEMB 36 16-Nov-09 Presentation on RPEs for equipment group RPEs; MP3 activity report and hardware commissioning;
TEMB 37 23-Nov-09 Sector seminars; MP3 activity report and hardware commissioning
TEMB 38 30-Nov-09 LHC beam commissioning status
TEMB 39 07-Dec-09 LHC beam commissioning status, training statistics

Next agenda

TEMB Home